Susan Moore 0 Report post Posted July 3, 2013 I have included the field, # of incomplete tasks, on my List of People Report and was getting inconsistent results. I then added the field, # of tasks, to the report and the numbers are identical. Why? Share this post Link to post Share on other sites
Michael Hannah 0 Report post Posted July 4, 2013 If all of your tasks are considered incomplete, then that number would be the same as the number of tasks. A task is considered incomplete until a valid date is entered in the "Completed" date field for that task. Share this post Link to post Share on other sites
Jim Byram 0 Report post Posted July 4, 2013 The report is apparently bugged. Even when a task has a completed date, it shows up in the incompleted count. Share this post Link to post Share on other sites
Susan Moore 0 Report post Posted July 4, 2013 I actually have people with 1 or more tasks: 63 that are complete that are listed as incomplete 3 that are incomplete that are listed as complete 111 that are correctly listed as incomplete. So this means that I need to wait for an update to TMG that will fix the problem? Share this post Link to post Share on other sites